This
section aims to delve deeper into the analysis of community aid
received by Gipuzkoa during the period 1986-1999 and that is managed
by the Diputación Foral de Gipuzkoa both for actions promoted
by the DFG itself and by Gipuzkoa municipalities.Community financing
directly obtained and managed by city halls is not taken into account.
|
In
this programme period, global funding amounts to 6,577.9 million
pesetas, of which 4,737.8 million pesetas (72%) come from the ERDF
through objective 2; 922.1 million pesetas (14%) come from the ESF
(through objective 2 and from objective 3) and 918 million pesetas
(14%) correspond to community initiatives (including the customs
reconversion plan).
|
|
|
|
Table
4.2. Global Funding (1989-1993)
(million
ptas.)
Period
|
Objective
2
|
Obj.
3
|
Com.
Inic.
(2)
|
Ayuntamientos
|
Total
89-93
|
ERDF
|
ESF
|
ESF
(1)
|
ERDF
|
ESF
|
Com.
Inic.
(3)
|
89-91
|
820,0
|
133,8
|
171,6
|
108,9
|
--
|
--
|
--
|
1.234,3
|
92-93
|
3.334,5
|
290,5
|
326,2
|
700,7
|
583,3
|
--
|
108,4
|
5.343,6
|
TOTAL
|
4.154,5
|
424,3
|
497,8
|
809,6
|
583,3
|
--
|
108,4
|
6.577,9
|
|
(1)
Includes old objective 4
(2) Includes Others: customs reconversion plan
(3) In this case only INTERREG II.
|
|
|
|
|
Of
ERDF financing, 4,154.5 million pesetas correspond to projects managed
by the Diputación Foral de Gipuzkoa and 583.3 million pesetas
correspond to projects managed by city halls. Regarding ESF financing,
424.3 million pesetas are through objective 2 and 497.8 million
through objective 3.
|
|
|
|
4.2.1.
Funding received through the ERDF (1989-1993)
In the period 1989-1991, Gipuzkoa receives, through the ERDF, funding
to the amount of 820 million pesetas, which is distributed along
two action axes: protection and improvement of the environment (with
525 million for water supply and treatment); and improvement of
the transportation network (with 295 million pesetas for the
Gipuzkoa-Navarra expressway).
|
|
|
|
Table
4.3. BCOP 1989-1991: Objective 2 (ERDF).
Volume of aid granted
ACTION
AXES
|
million
pesetas.
|
AXIS
2: Protection and improvement of the en-vironment
Water supply and treatment
|
525,0
|
AXIS
4: Improvement of transport network
Gipuzkoa-Navarra
expressway
|
295,0
|
TOTAL
|
820,0
|
|
|
|
|
With
respect to the period 1992-1993, global funding through the ERDF
(projects developed by the Diputación Foral de Gipuzkoa)
amount to 3,334.5 million pesetas, with 1,682.6 million pesetas
for water supply and treatment,
|
824.3 million pesetas for the creation and development of productive
activities (fundamentally industrial land), 433.6 million pesetas
for research and development and 394 million pesetas for improving
highways.
|
|
|
|
Table
4.4. BCOP 1992-1993: Objective 2 (ERDF).
Volume of aid granted (Diputación Foral de Gipuzkoa)
ACTION
AXES
|
Million
ptas.
|
1:
Creation and development of productive activities
Endogenous
development
Industrial complexes
|
141,7
682,6
|
2:
Protection and improvement of the environment
Water
supply and treatment
|
1.682,6
|
3:
Research and Development
R&D
Equipping R&D centres
|
122,3
311,3
|
4:
Improvement of Transportation
Highways
|
394,0
|
TOTAL
|
3.334,5
|
|
|
|
|
Regarding projects developed by city halls in Gipuzkoa, financing
received through the ERDF in the period 1992-1993 amounts to 583.3
million pesetas,
|
destined
to creating and developing productive activities (468.9 million
pesetas) and protecting and improving the environment (114.4 million
pesetas).
|
|
|
|
Table
4.5. BCOP 1992-1993: Objective 2 (ERDF).
Volume of aid granted (City Halls in Gipuzkoa).
ACTION
AXES
|
Million
ptas.
|
1:
Creation and development of productive activities
Endogenous
development (Irun)
Kursaal (San Sebastian)
Industrial land (Irun)
|
81,5
223,0
164,4
|
2:
Protection and improvement of the environment
Rehabilitation
of Niessen (Renteria)
Txingudi water treatment (Irun)
|
41,9
72,5
|
TOTAL
|
583,3
|
|
|
|
|
4.2.2.
Funding received through the ESF (1989-1993)
Financing received through the ESF in the period amounts to 952,8
million pesetas, 424.3 million through objective 2, 497.8 million
pesetas through objective 3 and 30.7 million pesetas through the
multiregional framework (customs). ESF financing via objective 2
is destined to support employment and competitiveness, while financing
through objective 3 goes for insertion in the labour market, fundamentally
of unemployed and disabled persons.
|
|
|
|
Table
4.6. Global ESF Funding (1989-1993)
(million
ptas.)
Period
|
OBJETIVE
2
|
OBJETIVE
3-4 |
TOTAL
1989-1993
|
89-91
|
133,8
|
171,6
|
305,4
|
92-93
|
290,5
|
326,2
|
616,7
|
TOTAL
|
424,3
|
497,8
|
922,1
|
|
|
|
|
|
|
4.2.3.
Funding received through COMMUNITY INITIATIVES (1989-1993)
In this period, Gipuzkoa also receives funding through Community
Initiatives. Particularly this funding is channelled through INTERREG
(160.2 million pesetas), RESIDER 1 -Adapted- (471.3 million pesetas),
NOW (39.2 million pesetas) and EUROFORM (13.6 million pesetas).
The total funding amounts to 684.3 million pesetas. The RESIDER
programme represents 75% of the financing that Gipuzkoa receives
in the period 1989-1993 through Community Initiatives.
|
|
|
|
Table
4.7. Community Initiatives (Volume of aid obtained)
(million
de ptas.)
INTERREG
I
|
ZAISA
(DFG)
Support training (DFG)
ZAISA (city halls)
Strategic planning (city halls)
Water treatment in Txingudi (city halls)
TOTAL
|
41,6
10,2
41,6
16,8
50,0
160,2
|
RESIDER
I (Adapted)
|
Equipping
training centres
Industrial land
TOTAL
|
317,8
153,5
471,3
|
NOW
|
Reinsertion
of women into the labour market
|
39,2
|
EUROFORM
|
Control
and management of quality
|
13,6
|
TOTAL
|
684,3
|
|
|
|
|
|
Financing received through Customs Re-Conversion (1989-1993)
Together with financing from the ERDF, ESF and the Community Initiatives,
Gipuzkoa also received supplementary financing in relation to the
customs reconversion plan, concretely 233.7 million pesetas, 60.8
for training and 172.9 million through norm 3904/92 (reconversion
to new economic activities).
|
|
|
|
Table
4.8. Customs (Volume of aid obtained)
(million
ptas.)
CUSTOMS
|
Customs
reconversion plan
(training area. ESF)
Customs reconversion plan
(norm. 3904/92)
|
60,8
172,9
|
TOTAL
|
233,7
|
|
|